Friday, 4 October 2013

Weekly Build update

30/9/13 
Outdoor lights and fan installed

3/10/13 
Fly screens and fly doors installed 


Finalised our wardrobe design! 


4/10/13
PCI - all went well only a few minor things were found. 
# There was an imperfection on a kitchen cupboard door. 
# The fans that were installed didn't have the switch to tune on and off.
# Few paint touch ups 

Overall very happy with the house! 

Handover next Friday the 11/10/13. Appliances will be installed after the 15th as the range hood was out of stock. 

Booked the delivery of our tiles for the Friday arvo. 

Tiler starts Saturday 12/10/13

5/10/13 
Carpet shopping. 