Sunday 15 December 2013

Countdown to move in date!

15/12/13
Range hood finished getting installed 


17/12/13
Form work done for a new gutter and driveway access. 


17/12/13
Footing and gutter poured 



18/12/13 Retaining wall blocks started 
Day 2




Monday 2 December 2013

Post Build Update

Countdown to Boxing Day as it will be our 1st night in our new home.

Been busy moving boxes and furniture the last couple of weeks and turning the house into our home. We had most stuff in storage for the past 4 years... so you can imagine the excitement seeing your possessions after such a long time. 

2/12/13 shutters installed! Looks stunning:) very happy! Money well spent! 



3/12/13 
Antenna installed 

4/12/13
Footing for the retaining wall dug out and planed out driveway and path. 



5/12/13 
Concrete pour didn't happen, as it pissed down for like two hours in the morning :(