Tuesday 30 July 2013
Friday 26 July 2013
26th July 2013 Roof commenced :)
The roof started to be put on today, My Dad managed to get the guys to take some pics from up on the roof:) looks so high!! Should be finished on Monday weather pending!
Sunday 21 July 2013
22nd July 2013 Gutter and Fascia install
Big Day on site! Site clean up, Paperbark Fascia and Jasper Gutter put up! Roof and Insulation arrived today!
Fascia and Gutter
Thursday 18 July 2013
17th - 19th July 2013 Brick work finished
Last few bricks going up today! The brickies have done an Awsome job and I was surprised to see them still on site at 16:45 :) We are very happy with the colour and the facade.
Monday 15 July 2013
15th - 16th July 2013
Brick update :) the fence side and the back of the house is completed! All that's left to do it the front of the house and the Alfresco pillars.
Tuesday 9 July 2013
9th July 2013
FernAir made contact with us to advise that they will be installing the 19.3kW ACTRON AIR System SRV203 to our home. We just needed to confirm the zones and where we wanted the outlets.
Monday 8 July 2013
Monday 1 July 2013
2nd July 2013 Bricks have commenced :)
After having so much rain over the past couple of weeks and the sun coming out for a total of 7 hours over an 8 day period.... Our SS has advised us, that the brick work has commenced today on the back side of the house:))