Friday 30 August 2013
Build Update 31st August 2013
We went past the house and was very surprised to see the guys working on a Saturday. We went in and met the tiler and checked the tiles.
Monday 26 August 2013
Wednesday 21 August 2013
21st August 2013 Lock up this arvo or tomorrow I'm guessing!
Front Door (will be painted the paperbark colour) and the Internal doors were fitted, Skirting boards and window architraves were also done today!
Tuesday 20 August 2013
Monday 19 August 2013
Wednesday 14 August 2013
14th August 2013
Water tank arrived and most of the Gyprock is done, the guys said they should finish some time Friday morning!
Water tank colour is paperbark
Family and Home Theater
Kitchen and Home Office
Laundry
Hallway and Kids area
Hayden's room
Kirra's room
Water tank colour is paperbark
Family and Home Theater
Kitchen and Home Office
Master Bedroom
Laundry
Hallway and Kids area
Hayden's room
Kirra's room
Dylan's room
Bathroom
Sunday 11 August 2013
7th - 9th August 2013
Insulation, Cornices and Gyprock delivered. Looked
like most of the Insulation was installed to
the walls!
Sunday 4 August 2013
5th August 2013 Electrical Walk through
Just had our 1st official walk through of the house to check the electrical, everything was correct. The eves were done late last week and the bricks were cleaned today!